Correct the start and status dates

  1. In the Query dialog box, note the name of the column containing the invalid date.
  2. Select the record with the invalid date, and then click OK.

    The Investigation dialog box populates with information about that investigation, and displays the information on the Basic tab.

  3. In Start Date or Status Date, correct the date.
  4. In the Investigation dialog box, click Save.
  5. Continue with Check for invalid dates in investigation records.